Define your optimal sprint duration and plan your sprints until project end using Global Sprint Plan Table 1.
| Sprint | Start | Finish |
|---|---|---|
| 1 | 20.02.2020 | 26.02.2020 |
| 2 | 27.02.2020 | 04.03.2020 |
| 3 | 05.03.2020 | 11.03.2020 |
| 4 | 12.03.2020 | 18.03.2020 |
| 5 | 19.03.2020 | 25.03.2020 |
| 6 | 26.03.2020 | 01.04.2020 |
| Easter Holiday | ||
| 7 | 09.04.2020 | 15.04.2020 |
| 8 | 16.04.2020 | 22.04.2020 |
| 9 | 23.04.2020 | 29.04.2020 |
| Students Week | ||
| 10 | 07.05.2020 | 13.05.2020 |
| 11 | 14.05.2020 | 20.05.2020 |
| 12 | 21.05.2020 | 27.05.2020 |
| 13 | 28.05.2020 | 03.06.2020 |
| 14 | 04.06.2020 | 10.06.2020 |
| 15 | 11.06.2020 | 17.06.2020 |
| 16 | 18.06.2020 | 23.06.2020 |
Build your project backlog, including all relevant tasks/deliverables, using Project Backlog Table 2. Prioritize all backlog items (PBI), keeping higher priority items at the top, and lower priority at the bottom.
| PBI | Title | Status |
|---|---|---|
| J | List of Materials | To do |
| D | Structural Drafts (CAD) | To do |
| C | Black Box (complement → comm. class) | To do |
| P | Project Development | To do |
| Q | Flyer and Leaflet (adjust) | To do |
| H | Market Research | To do |
| G | Project Management | To do |
| I | Sustainability | To do |
| B | Project Planning | To do |
| E | Interim Report | To do |
| K | Functional Tests | To do |
| L | Final Report | To do |
| N | Implement Design Thinking | Done |
| A | State of the Art | Done |
| F | Name and Logo | Done |
| O | Ethics | Done |
| M | Cardboard model | Done |
Plan each sprint at its beginning (Sprint Planning session) using the Sprint Plan Table 3.
| Sprint | Task | Duration (d) | Responsible | Involved |
|---|---|---|---|---|
| 1 | B | 7 | Lore | Jelte, Andreea |
| 1 | C | 2 | Jelte and Andreea | / |
| 1 | P | 28 | Andreea, Lore | Gabriel, Eduardo |
| 1 | N | 2 | Jelte | / |
| 1 | A | 14 | Jelte | Lore, Andreea, Gabriel, Eduardo |
| 2 | H | 14 | Vladimir, Gabriel | Andreea, Jelte |
| 2 | F | 5 | Andreea | / |
| 2 | G | 8 | Andreea | Lore |
| 2 | I | 14 | Jelte | Gabriel |
| 2 | O | 7 | Lore, Andreea | Eduardo |
| 2 | M | 5 | Lore | / |
| 2 | D | 5 | Eduardo | Lore, Andreea |
| 2 | J | 7 | Eduardo, Gabriel | Andreea, Jelte, Lore |
| 3 | Q | 3 | Andreea | Lore |
Review each sprint at its end and update each item status on the Progress Register Table 4.
| Sprint | PBI | Responsible | Involved | Status |
|---|---|---|---|---|
| 1 | B | Lore | Jelte, Andreea | Done |
| 1 | C | Jelte and Andreea | / | To adjust |
| 1 | P | Lore, Andreea | Gabriel | In progress |
| 1 | N | Jelte | / | Done |
| 1 | A | Jelte | Andreea, Lore, Gabriël, Eduardo | Done |
| 2 | H | Vladimir, Gabriel | Andreea, Jelte | In progress |
| 2 | F | Andreea | / | Done |
| 2 | G | Andreea | Lore | In progress |
| 2 | I | Jelte | Gabriel | In progress |
| 2 | O | Lore, Andreea | Eduardo | Done |
| 2 | M | Lore | / | Done |
| 2 | D | Eduardo | Lore, Andreea | In progress |
| 2 | J | Eduardo, Gabriel | Andreea, Jelte, Lore | In progress |
| 3 | Q | Andreea | Lore | In progress |
Gantt Chart