EPS@ISEP | The European Project Semester (EPS) at ISEP


Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
plan [2020/03/13 22:47] – [Project Plan] team3plan [2021/03/23 11:23] (current) – external edit 127.0.0.1
Line 6: Line 6:
   * 2020-03-05 Define the **Project Backlog** (what must be done and key deliverables - every member should preferably participate in every task), **Global Sprint Plan**, **Initial Sprint Plan** (which tasks should be included, who does what) and **Release Gantt Chart** of the project and insert them on the wiki (planning)   * 2020-03-05 Define the **Project Backlog** (what must be done and key deliverables - every member should preferably participate in every task), **Global Sprint Plan**, **Initial Sprint Plan** (which tasks should be included, who does what) and **Release Gantt Chart** of the project and insert them on the wiki (planning)
   * 2020-03-10 Upload the “black box” **System Diagrams** & **Structural Drafts** to the wiki   * 2020-03-10 Upload the “black box” **System Diagrams** & **Structural Drafts** to the wiki
-  * 2020-03-20 Upload the detailed **System Schematics Structural Drawings** to the wiki and do the **cardboard scale model** of the structure +  * 2020-03-27 Upload the detailed **System SchematicsStructural Drawings & 3D Modelation** to the wiki and do the **cardboard scale model** of the structure 
-  * 2020-03-25 Upload the **List of Materials (what & quantity)** to the wiki +  * 2020-04-01 Upload the **List of Materials (what & quantity)** to the wiki 
-  * 2020-03-27 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Eco-efficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. In particular, the Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart  +  * 2020-04-08 Upload the **Interim Report and Presentation** to the wiki. The report must contain the the following chapters: Introduction, Project Management, State of the Art, Marketing Plan, Eco-efficiency Measures for Sustainability, Ethical and Deontological Concerns, Proposed Solution and Bibliography. In particular, the Project Management chapter includes the updated project progress register, the sprint report for completed sprints (tasks that were included, statuses, assignees, allocations) and the updated release Gantt chart  
-  * 2020-04-02 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks +  * 2020-04-16 Interim Presentation, Discussion and Peer, Teacher and Supervisor Feedbacks 
-  * 2020-04-22 Complete the **List of Materials (local providers & price, including VAT and transportation)** to the wiki +  * 2020-04-23 Upload the **List of Materials (provider, price, quantity, including VAT and transportation)** to the wiki 
-  * 2020-05-29 Upload refined Interim Report (based on Teacher & Supervisor Feedbacks) +  * 2020-04-30 Upload the **Final video of the 3D Model** to the wiki  
-  * 2020-06-02 Upload the results of the **Functional Tests** to the wiki +  * 2020-05-06 Upload **Refined Interim Report (based on Teacher & Supervisor Feedbacks)** to the wiki 
-  * 2020-06-12 Upload the **Final Report, Presentation, Video, Paper, Poster and Manual**+  * 2020-05-13 Upload **Packaging solution** to the wiki 
 +  * 2020-06-02 Upload the results of the **(Prototype or Simulation) Functional Tests** to the wiki 
 +  * 2020-06-12 Upload the **Final Report, Presentation, Video, Paper, Poster and Manual** to the wiki
   * 2020-06-16 Final Presentation, Individual Discussion and Assessment   * 2020-06-16 Final Presentation, Individual Discussion and Assessment
-  * 2020-06-19:+  * 2020-06-22:
     - Update the wiki, report, paper with all suggested corrections     - Update the wiki, report, paper with all suggested corrections
-    - Hand in to the EPS coordinator+    - Upload to the OneDrive folders shared by epsatisep
-      - a **Pendrive with the refined deliverables (source + PDFtogether with all code and drawings produced** +      - Deliverables (pdf and others) 
-      - a **printed copy of the refined report and poster**+      - Code (Arduino code, Tinkercad/CoppeliaSim simulation code, mobile and Web app code) 
 +      - CAD (drawings and 3D model files) 
 +      - Videos (3D model simulation and final team video in mp4)
   * 2020-06-23:   * 2020-06-23:
-    - Hand in the **prototype and user manual** to the client+    - Play **final video** 
 +    - Play **music/landscapes** of your country
     - Receive the **EPS@ISEP certificate**     - Receive the **EPS@ISEP certificate**
-    - Bring **typical food** from your country 
- 
- 
 ===== Project Plan ===== ===== Project Plan =====
  
Line 64: Line 66:
 <caption>Project Backlog</caption> <caption>Project Backlog</caption>
 <WRAP box 400px center> <WRAP box 400px center>
-^ PBI       ^ Title          ^ Status     ^ +^ PBI       ^ Title          ^ Status              
-        | Project Planning    | To do      |    +        | List of Materials    | To do      | 
-| C         | Black Box       | To do      |       +| D         | Structural Drafts (CAD)    | To do      |   
-| D         | Structural Drafts    | To do      |   +        | Black Box (complement -> comm. class)      | To do      |     
-        | Impement Design Thinking    | To do      |  +        | Project Development       | To do      |  
-        | State of the Art    | To do      |   +        | Flyer and Leaflet (adjust)   | To do      |
-        | Updating Gantt Chart    | To do      |+
 | H         | Market Research    | To do      |    | H         | Market Research    | To do      |   
 | G         | Project Management | To do      |    | G         | Project Management | To do      |   
-| I         Ecological Research    | To do      |    +| I         Sustainability    | To do      |      
-        | List of Materials    | To do      |  +        | Project Planning    | To do      |  
-| F         | Name and Logo   | To do      |   +| E         | Interim Report | To do      |  
-| E         | Interim Report | To do      |   +
 | K         | Functional Tests    | To do      |  | K         | Functional Tests    | To do      | 
-| L         | Final Report | To do      |   +| L         | Final Report | To do      |   
 +| N         | Implement Design Thinking    | Done      | 
 +| A         | State of the Art    | Done      |  
 +| F         | Name and Logo   | Done      | 
 +| O         | Ethics    | Done      |  
 +| M         | Cardboard model    | Done      |
  
 </WRAP> </WRAP>
Line 90: Line 95:
 <WRAP box 400px center> <WRAP box 400px center>
 ^ Sprint    ^ Task  ^  Duration (d) ^  Responsible ^ Involved   ^ ^ Sprint    ^ Task  ^  Duration (d) ^  Responsible ^ Involved   ^
-| 1         | B                 | Lore      | Jelte, Andreea |   +| 1         | B                 | Lore      | Jelte, Andreea |   
-| 1         | C                 | Jelte and Andreea            | / |     +| 1         | C                 | Jelte and Andreea            | / |     
-| 1             | 3             | Gabriël   | Andreea, Lore |+| 1             | 28            | Andreea, Lore   | Gabriel, Eduardo |
 | 1         | N     | 2             | Jelte      | / | | 1         | N     | 2             | Jelte      | / |
-| 1         | A     7             | Jelte            | Lore, Andreea, Gabriël, Eduardo |   +| 1         | A     14            | Jelte      | Lore, Andreea, Gabriel, Eduardo |    
-        |     | 5             | Lore | Jelte |  +| 2         | H     | 14            | Vladimir, Gabriel | Andreea, Jelte |   
-        |     | 5             Vladimir | / |  +        |     | 5             | Andreea | / |  
 +| 2         | G     | 8             | Andreea | Lore  |  
 +| 2         | I     | 14            | Jelte| Gabriel |  
 +        | O     | 7             | Lore, Andreea| Eduardo 
 +| 2         | M     | 5             Lore | / | 
 +| 2         | D     | 5             | Eduardo| Lore, Andreea  
 +| 2         | J     | 7             | Eduardo, Gabriel | Andreea, Jelte, Lore | 
 +| 3         | Q     | 3             | Andreea | Lore | 
 </WRAP> </WRAP>
 </table> </table>
Line 108: Line 121:
 ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^ ^ Sprint    ^ PBI   ^ Responsible  ^ Involved   ^ Status      ^
 | 1         | B     | Lore      | Jelte, Andreea | Done        |  | 1         | B     | Lore      | Jelte, Andreea | Done        | 
-| 1         | C     | Jelte and Andreea            | / | Done             +| 1         | C     | Jelte and Andreea            | / | To adjust             
-| 1             | Gabriël   | Lore, Andreea | In progress        |  +| 1             | Lore, Andreea   | Gabriel | In progress        |  
-| 1         | A     | Jelte            | Andreea, Lore, Gabriël, Eduardo | In progress |  +| 1         | N     | Jelte   | / | Done        | 
-        |     | Jelte      | / | In progress |   +| 1         | A     | Jelte   | Andreea, Lore, Gabriël, Eduardo | Done |  
-        | M     | Lore | Jelte | In progress |+| 2         | H     | Vladimir, Gabriel      | Andreea, Jelte | In progress |   
 +        |     | Andreea      | / | Done | 
 +| 2         | G     | Andreea      | Lore | In progress | 
 +2         | I     | Jelte      | Gabriel | In progress | 
 +| 2         | O     | Lore, Andreea      | Eduardo | Done | 
 +| 2         | M     | Lore |/ | Done | 
 +| 2         | D     | Eduardo | Lore, Andreea| In progress | 
 +| 2         | J     | Eduardo, Gabriel | Andreea, Jelte, Lore | In progress | 
 +| 3         | Q     | Andreea |Lore | In progress |
  
 </WRAP> </WRAP>
Line 121: Line 142:
 **Gantt Chart** **Gantt Chart**
  
-{{ ::gantt-chart_.xlsx |}}+{{ :gantt-chart_4.pdf |}}
  
QR Code
QR Code plan (generated for current page)